![]() |
|
New Town Hall Project |
|
||||||||||||||
| It was then suggested that we build a combined
garage and new town hall together to take advantage of the lower
materials and construction costs that are present today. On June
17, 2008, a public meeting was held to discuss the issue of building
this new structure and only about six property owners attended.
Those folks voted to proceed with the building project this fall due
to lower construction costs and approved the hiring of an architect to
draw up plans needed for the permit application with Crow Wing
County. We also began the process of assembling a package for
bidders for the construction part of the project and an advertisement
for sealed bids was published on June 24 and July 1, 2008. The
bid opening was scheduled for July 10th just prior to our regular
meeting.
The sealed bids received were opened on July 10, 2008 and the board voted to reject all bids due to the high cost of building reflected in the bids. Bids ranged from $232,000 to $308,00 and two companies did not provide a bid due to problems with the plans and specifications. Part of the reason for the cost overrun was due to erroneous building specifications that were not needed but were incorporated into the bid documents derived from the plans provided by the architect. Bid opening minutes are here. At the August 14th regular meeting, the board heard more comment and again discussed the cost of building and the issue of perhaps placing the question to build on the November election ballot to better reflect the opinion of more of the Town's residents who will be paying the costs of the project. This would be an option that the Board could exercise even though the statutory requirements have been met regarding procedural issues pertaining to the discussions and the Board's decision to proceed with this project. A valid argument can be made that because of the higher than anticipated building costs as reflected in the bids received, it would be appropriate to place this issue on the November ballot. It should also be noted that those costs to build will likely be greatly reduced through a revised bid process involving a better definition of the plan of work, bidder responsibility and improved cost controls through a revision of the bid package design and content. To See the Progress, Click these links: PHOTOS
PAGE 1 PHOTOS PAGE
2 PHOTOS PAGE 3
PHOTOS PAGE 4 PHOTOS PAGE
5 |